Last Friday the demolition team made good headway. The day was all about breaking up and removing the old concrete paths and foundations, ready for the next stages of the build.
Breaking and peeling
The 3-tonne excavator did most of the work, fitted with a small rock breaker. The technique is called "stitching": the breaker chips a line through the concrete path to weaken it, then the machine's ripper peels up whole slabs and folds them back on themselves. All of the old 100 mm path has now been pulled up and piled, broken into smaller pieces, and loaded into a skip.
Neighbours, vibration and water
The old pool area had very thick concrete. The main issue there is vibration, which travels easily through sandy soil to the neighbouring properties.
To keep it down, we're deliberately using the smaller 3-tonne excavator instead of a much larger machine. We're being as gentle as we can, but breaking concrete is always a noisy, heavy job.
The other challenge is the high water table. Soil tests show groundwater about 1.6 metres down, so once we dig to that level we'll be dealing with water. That means dewatering (pumping the groundwater out with spear points or a sump pump), which adds cost and time. We explain how spear points work in Post 7. If your soil report shows a high water table, budget for it early.
Detail work and a design change
Some areas need extra care. The old stairs appear to be pinned into the boundary wall, so they'll need careful stitching with the rock breaker and some final removal by hand. We also found a large, thick concrete footing that was probably built to protect the seawall.
We also met the engineer last week and made a sensible change to the pool plan. Instead of digging a deep void under it, we'll keep the existing ground, build a retaining wall and a new slab, and sit the pool on top. That better protects the seawall next to it from structural stress.

What's next
We also finished a few other jobs. The irrigation to the protected tree is done, and its trunk is wrapped to keep it moist. A second shade area is finished too, which is handy for our Friday site barbecues.
Next, we'll pull out the remaining rotten framing by hand and tackle the thick edge beams of the old slab, which need more precise rock breaking. All going well, the demolition and preparation should take about another 10 days.


