Welcome to our new series, where we pull back the curtain on our latest development projects. A lot has been happening behind the scenes, and we're glad to finally share it with you.
Our two new projects
For the past 11 months we've been laying the groundwork for two new developments. This project starts once we have Development Approval (DA, the council's planning approval). After that, the certifier can issue an early works Building Approval (BA, the approval to build).
This first post is all about Project #1
It's a residential house (a Class 1a building under the National Construction Code, which just means a standalone house) that we're building to commercial-grade standards: tighter tolerances, more engineering and documentation, and more rigorous inspection than a typical house. (Project #2 is a Class 2 building, meaning apartments, and we'll cover that later.)
Our goal with this series is simple: to show you the what, how and why of what we do. We'll walk you through our processes up close and explain the reasoning behind the materials we choose and the methods we use.
Project overview: from the ground up
So what exactly is Project #1? For the last 11 months our focus has been on the groundwork you don't see: project management, contract administration and a lot of planning.
On this project we wear two hats. The first is Client-Side Project Manager and Developer. In this role we organise everything needed to turn the initial idea into an approved, ready-to-build project.
The second hat is Construction Manager and Builder. Once enough of the plans are set and the DA and BA are issued, we switch to organising and carrying out the construction.
The scope is to demolish the existing house and build a new one with a basement plus three storeys above ground.
Since November 2024 we've been deep in preliminary design with our full team of consultants: the architect, structural engineer, civil engineer and more. After countless meetings, we're finally nearing the point where physical work on site begins.
Showing, not just telling
We think the best way to share this process is to show you each step as it happens.
We've set ourselves up with lavalier mics and receivers and started filming on site. The format is simple: we walk the site and talk you through what's happening, explaining the discussions and decisions behind our work, from material selection to construction methods.
I also want to be upfront about our approach. Like all builders, we have our own preferences and biases based on past experience. The way we build is our way, but it's certainly not the only way. This project will be built to the design created by our consultants, with our input and, most importantly, the client's vision.
Site overview: laying the groundwork
This week we began preparing the site. You might spot blue markings on the ground. They show the location and depth of underground services like water and power, which here run between 750 mm and 1.3 m deep. Knowing exactly where they are before any machine digs is the first safety step on any site.
What's next: demolition and early works
The next major milestone is demolishing the existing house and all other structures on the site. We've engaged a demolition contractor and are locking in a date, which we expect to be in early January 2026.
After that, the real transformation begins. The schedule includes:
- Sheet piling and dewatering: holding back the surrounding ground and pumping out groundwater so we can dig deep safely.
- Bulk excavation: removing about 2,000 m³ of earth to create the basement.
- Basement construction: the slab and walls that everything else stands on.
An Australian-first trial
We're also testing something new: a polymer used in the sheet piling process, and this is the first project in Australia to use it. Think of it as a high-tech lubricant that helps the steel sheets slide into the ground.
That's only a simple analogy; it does more than that. If the trial is successful, it could change the types of projects where sheet piling is a viable option. We're working closely with the sheet piling contractor and the geotechnical engineer on it.
A long build, shown openly
This is a significant build: a large house that we expect to take about 2 to 2.5 years. We'll share each stage, from the drawing board to the finished home, including the advanced construction methods, detailed inclusions and high level of finish that go into a house like this.
Next up is Post 2, our first walk around the site.
A quick note on our quality checklists: the full library is now available, including the C15 Painting Inspection Checklist. See all our checklists.
Thanks for following along.
Regards,
Anthony


