Welcome back to a tired person filming. Last time (Post 58) was the core fill pour. Since then we've stripped the site, restocked, and started waterproofing the outside of the basement walls.

Stripping everything the day after the pour

On the Saturday, the day after the pour, we stripped all of the back props. That took five of us from 6:30 until 2:30.

Everything gets stacked so it can be used again:

  • LVLs stacked. They still need cleaning, but that's an easy job for another day.
  • Dunnage and timbers set aside. We keep about fifty 90 x 35s in stock for general use, and later on they'll go into the house.
  • The little profile timbers from the first videos. We've used them a lot as packers for props.

We try to get at least three uses out of everything, if not more. The offcuts went onto what I call my sacrificial pyre, and then we cleaned everything again, inside and out, because it was a pigsty.

A cheap tip while I'm here: those little two litre Halloween buckets from Bunnings. We use them for screws when we strip the formwork, so we can sort them and reuse them all.

The walls stripped back: push pull props still in, starter bars capped and the floor swept
The walls stripped back: push pull props still in, starter bars capped and the floor swept

More Rediwall, a crane and a telehandler

We had another AFS delivery, because we used the last lot. This one is mainly RW200 for the internal walls. A couple of those walls at the back hold up important slabs, so they come first. One of them is a curved wall, built from curved and straight pieces, and it carries a small slab that has to be done before the big ground floor slab can go on.

The new RW200 panels stacked on the basement slab, with the braced RW275 wall behind
The new RW200 panels stacked on the basement slab, with the braced RW275 wall behind

A 55 tonne slew crane lifted the AFS panels down, along with the Bidim and the waterproofing, and flew out a scissor lift. Lifting the 7 tonne telehandler in is a different story: more than 10 metres out, it really needs a 55 to 70 tonne crane, and the one we had was a bit small. Instead, we'll build a stone ramp and drive the telehandler in.

The telehandler has a bucket, and that's what we'll use to place the 5 mm gravel behind the walls. The transport company is sending one truck at a time on about a one hour turnaround, around 8 to 10 cubic metres a load. We need about 150 to 190 cubic metres in total.

Waterproofing starts with prep

Waterproofing, like most things, doesn't start with the product. It starts with prep.

First we swept, blew and vacuumed the whole area again, about the tenth time, getting out as much dust and rubbish as possible. Then we ground the concrete back with a flat disc and cleaned the Rediwall with xylene. Not a fun chemical, but it's what Sika asked for on the PVC.

The junction: band, cove and primer

The most important part is where the wall meets the slab. That's where water wants to get in, so that's where we go to town on it.

  • The band. First we set WPA Elastoband into Sikadur-31 epoxy along the junction and let that go off.
  • The cove. Then we came back and ran a 40 mm Sikadur-31 cove over the top of it. Coving is just the little radius in the corner, so the membrane doesn't have to bend over a sharp edge.
  • The primer. Then Sika Indever SP, a black bitumen primer, on the concrete where the membrane laps onto it.

That's two laps of the junction, about 240 linear metres all up. My back has decided it wants to part company with me.

Where the wall meets the slab: WPA Elastoband in epoxy first, a 40 mm Sikadur-31 cove over it, Sika Indever SP primer on the toe, the E40 sheet lapped 150 mm onto the slab, the HW 2010 waterstop central under the wall and Xypex Admix C-5000 in the core fill
Where the wall meets the slab: WPA Elastoband in epoxy first, a 40 mm Sikadur-31 cove over it, Sika Indever SP primer on the toe, the E40 sheet lapped 150 mm onto the slab, the HW 2010 waterstop central under the wall and Xypex Admix C-5000 in the core fill
Primed concrete in black, where the membrane will lap down onto it, ducking under the capped starter bars
Primed concrete in black, where the membrane will lap down onto it, ducking under the capped starter bars

The peel and stick sheet

The membrane is SikaShield E40, a 1.5 mm peel and stick bituminous sheet with an HDPE face. It sticks to the plastic of the Rediwall once it's been wiped clean, and it laps down onto the primed concrete at the bottom.

  • Laps of 75 to 100 mm between sheets.
  • A pressure roller over every sheet and every lap. We'll give it all another good roll before the gravel comes in.
  • Two people is the easiest way to hang it, because it's very sticky and you don't want it sticking to itself.
  • Corners get lapped and sealed in layers. I'm not good at wrapping Christmas presents, and it shows.
Laying the sheets: 1.0 m rolls, each lapping the last by 100 mm, pressure rolled, and 150 mm down onto the slab toe
Laying the sheets: 1.0 m rolls, each lapping the last by 100 mm, pressure rolled, and 150 mm down onto the slab toe
The sheet on the wall in the gap beside the sheet piles
The sheet on the wall in the gap beside the sheet piles
Looking down on an outside corner, the sheet lapped onto the slab toe
Looking down on an outside corner, the sheet lapped onto the slab toe

Over the membrane goes Bidim A39G, a Geofabrics geotextile that stops the stones puncturing the waterproofing. At the top it's held with an aluminium termination bar. We'll flick a line and fix the bar with M6 x 50 mm masonry anchors. The walls are nearly 300 mm thick, so a 50 mm anchor goes nowhere near through.

Why there's no ag drain

Most people expect an ag drain behind a basement wall. We don't need one here. These walls sit below the water table, so they'll be under water all the time, up to about 1.6 metres above the slab.

There's nowhere for that water to drain to. An ag drain would just feed the water back to the tanks, and the pumps would run constantly. A good way to burn out a pump.

So instead of draining it, we seal it. Rediwall advise that filled panels resist 8 metres of water pressure with the floor/wall junction sealed, and we've only got about 1.6. The concrete came up nicely after the vibrating in Post 58: not bony, not many holes, nice and compact.

Behind the wall: sheet pile, 5 mm gravel backfill, Bidim A39G over the E40 sheet, and the termination bar at the top
Behind the wall: sheet pile, 5 mm gravel backfill, Bidim A39G over the E40 sheet, and the termination bar at the top

Four lines of defence

Here's how the layers stack up:

  1. The SikaShield E40 sheet over the whole outside face.
  2. The Sikadur epoxy cove protecting the floor/wall junction.
  3. The waterstop. WPA HW 2010 hydrophilic waterstop is in the floor track under all of the RW275 walls.
  4. Xypex in the core fill. You can't see it, but we ordered it, it's on the docket and we're paying for it.
Four lines of defence: the E40 sheet, the epoxy cove, the hydrophilic waterstop in the floor track and Xypex Admix in the core fill
Four lines of defence: the E40 sheet, the epoxy cove, the hydrophilic waterstop in the floor track and Xypex Admix in the core fill

Where the stripped formwork left reo exposed, we'll treat it with Xypex Concentrate and then patch it with a Fosroc high strength repair mortar.

The tight side, spears and the ring main

The tightest spot on site is where the sheet piling goes around the tree. You can see the piles flex a little. That's normal. They're only about 5 mm thick, because they're a temporary retaining wall, not a permanent one.

Down there you can see the dewatering ring main that runs around the site, with the spears plugged into it. There's a capped-off spear as well. They put a few in just in case, and we can hook them back into the ring main if we ever need them.

The gap between the sheet piles and the wall: the dewatering ring main and spears on the left, primed concrete on the right
The gap between the sheet piles and the wall: the dewatering ring main and spears on the left, primed concrete on the right

The conduits coming out of the walls were taped off before the fill. If you don't tape something off, it's the first thing that gets accidentally filled with concrete.

What the gravel does next

The plan for the week: Saturday we stripped, Monday we started waterproofing, Tuesday more waterproofing, and Wednesday we finish it, hang the Bidim and start filling with rock.

The gravel does three jobs:

  • A working base to put the formwork on for the outside of the house and to form up the structural slab for the pool shell.
  • It locks in the sheet piling, pushing back against the two neighbours' houses so nothing moves around.
  • It pushes on the walls, so the props stay in. Nothing comes out until the engineer confirms it can.

Formwork for the ground floor arrives Friday, and then we're into the internal walls.

If you've had concrete poured on your own build, the C6 Post-Pour Slab Inspection Checklist shows you what to look at once the forms come off.

C6 - Post Pour Slab Inspection Checklist

$59.00 AUD

Last updated 28 Oct 2026 · Revision 4 · Free updates for life

Checklist Type: Minor

Form Factor: Fillable, print-ready PDF (A4, 21 pages)

When to use: After the concrete pour, before the frame goes up

A 61-point checklist to inspect your slab after the pour: records, curing, edges, levels, pipes and cracks, while repairs are still easy to arrange.

Preview C6

✓ Authorship verified on the blockchain · View certificate

See all our checklists

Buy C6 – $59