PROJECT 1
Post 27: Sheet Pile Installation
See how the team installed and aligned 7m sheet piles using vibration, checked plumb and square placement, adjusted to protect the fence line, and finished to the required RL—especially in tight access areas.
Post 26: Sheet Piling Site Update: Drainage Fixes, Recertification, and Vibration Monitoring
After heavy rain flooded the site, we had the platform re-certified by the geotech engineer. Today we added road base, improved drainage, and installed vibration monitoring so piling can start smoothly.
Post 25: Certified Platform complete
Good morning! Yesterday we completed the CBR Type 2.3 layer (300mm) and rolled it with minimal vibration. Today we met the geotech for a proof roll, found one soft spot, and arranged steel plates for safe piling and sheet piling.
Post 24: Creating Driveway Access for Truck Deliveries
Only a few trucks are running today while quarry deliveries arrive tomorrow. We’re compacting sand, rolling the driveway, and shaping a ramp so trucks can access the site safely—without getting stuck.