Post 23: Building a Certified Platform for Piling Works
Today’s work is focused on building a certified 250kPa platform to support a larger piling rig. The goal is to reduce vibration impacts on neighbouring homes and prepare the site for upcoming sheet piling works.
Post 22: Project 1: Piling platform preparation works: bulk excavation
An update on our platform preparation works, including bulk earthworks, excavation quantities, bearing platform requirements, and the next steps toward geotechnical certification.
Post 21: Project 1: Early Works Update: DA Secured, Sheet Piling Next
We’ve secured DA approval and are lining up insurance, sheet piling, and dewatering. Lots of paperwork and coordination now—visible progress begins once sheet piling and dewatering start.
Post 20: Project 1: Site update: planning, surveys, and preparations before major works
Behind-the-scenes site update: tie-downs, groundwater tests, survey orders, and the cost trade-offs between sheet piling and secant piles—plus why dewatering and backup power are critical.