Procurement sounds like office jargon, but it has a big effect on your new home. It's how your builder plans, orders and pays for everything needed to build your house: materials, trades and services. Done well, the right things arrive on time at the agreed price. Done badly, you get delays, substitutions and variations.

Most builders don't have a formal procurement team, but every good builder has a procurement process, even if it lives in the supervisor's head. Here's what it should look like and what to ask.

Why it matters to you

  • Price: under a fixed-price contract, the builder has priced the materials and trades up front. If their pricing was loose, the gaps tend to come back to you as provisional sum adjustments or variations.
  • Timeline: late windows, trusses or bricks hold up the whole job. One missed order can cost weeks.
  • Quality: good builders choose suppliers and trades for reliability and workmanship, not just the lowest price.

It starts in the design phase

The decisions made during design set up everything that follows. Your designer's choices of materials, products and structural system decide what has to be ordered, which trades are needed and how long things take.

A good designer works with the builder early, so the design is buildable within your budget and uses products that are actually available. Unusual imported products and one-off details are where procurement problems usually start.

Who does what at a project builder

You'll usually sign one contract with one builder. Behind that, a Queensland project builder typically has:

  • Sales consultant: your first contact. Takes you through designs, inclusions and the initial price.
  • Contract administrator: prepares the contract documents, processes your selections and variations, and confirms pricing.
  • Estimating and purchasing: prices the job and places orders with suppliers and trades.
  • Construction manager: oversees a group of site supervisors and steps in when problems come up on site.
  • Site supervisor: runs your build day to day, books the trades and deliveries, and checks the work.

On a smaller custom build, one or two people might do all of this. That can be a strength, as long as they're organised.

How procurement plays out through the build

Queensland contracts are paid in stages. Here's what needs to be ordered and coordinated for each:

  • Base: site set-out, earthworks, plumbing under the slab, and the slab or footings. Concrete, steel and termite protection need to be lined up.
  • Frame: wall frames and roof trusses, often with long lead times, plus bracing and tie-downs.
  • Enclosed: roof, windows and external doors, and external cladding or brickwork. Windows are a common hold-up.
  • Fixing: plasterboard, internal doors, cabinetry, skirting and architraves, and tiling. Cabinetry and stone benchtops need early measuring and ordering.
  • Practical completion: painting, fit-off of plumbing and electrical, final cleaning and defect fixes, ready for your inspection and handover.

At every stage, the builder should be checking the work before it's covered up.

Different ways of procuring a house

  • Traditional (design, then tender): you have plans drawn by an architect or designer, then get builders to price them. Clear specification and good cost control, but changes during construction can be expensive.
  • Design and construct: one company designs and builds, as most project builders do. Faster and simpler, but you have less independent control over the design.
  • Construction management: you engage a manager who engages the trades directly on your behalf. More control and flexibility, but more involvement and more risk on your side. It's uncommon for a single home.

For most homeowners, it's one of the first two.

What good procurement looks like

  • Clear specification: products, finishes and quantities are listed, not left as "builder's range" or vague allowances.
  • Realistic allowances: provisional sums and prime cost items are based on real prices.
  • Orders placed early: long-lead items are ordered as soon as your selections are confirmed.
  • Reliable suppliers and trades, with a backup when someone lets them down.
  • A plan for substitutions: if a specified product isn't available, you're told and asked first, with any cost change in writing.
  • Quality checks before work is covered.

Questions to ask your builder

  1. What are your current lead times for windows, trusses, bricks and cabinetry?
  2. Which items in my contract are provisional sums or prime cost items, and how were the allowances worked out?
  3. When do I need to finalise my selections so they don't hold up the job?
  4. What happens to my price and my program if a specified product isn't available?
  5. Who will supervise my build, and how many other jobs are they running?
  6. How do you check each stage before it's covered up?

The short version

Procurement is the behind-the-scenes work that decides whether your build runs on time and on budget. Get your selections done early, understand your allowances, and ask your builder how they manage lead times and substitutions before you sign.