Practical completion is the last time you see your new home before you accept it and pay the final claim. Anything you miss on the day becomes your problem to prove later. This post walks through our new C16 Practical Completion Inspection Checklist: what it is, what it does, when to use it, and what you get out of it.
Practical Completion: what to check before you accept the finished home
Start at the desk: book your inspector, gather the plans and variations, and sight the certificates.
Walk it in order: outside, roof, garage, then every room, wet area and service. Tick Fine, Later (couldn't check) or Issue.
List and agree: write every defect down, agree fix-by dates with the builder, and both sign. S13 lists what your builder should be doing: ask to see the records.
The 13 sections
- S1Before you goBuilder's written notice, the contract's practical completion clause, plans and variations, inspector booked, daylight and services on10
- S2Certificates hold pointFinal inspection, engineer, frame and truss, waterproofing, electrical, plumbing and gas, termite, glazing, energy, warranty15
- S3Outside walk-roundGround falls, slab height and exposed edge, drainage, weep holes, brickwork, cladding and paint, taps, lights, driveway24
- S4Steps, decks and balconiesRiser and going sizes, handrails and balustrade heights, decking, balcony falls and door sills, outdoor tiles10
- S5Roof and guttersGutters and fascia, falls, roof tiles or sheets, flashings and penetrations, eaves, solar, insulation, ducted fans12
- S6GarageDoor operation and safety reverse, floor falls and cracks, walls and ceiling, internal door, lights and power6
- S7Living rooms and bedroomsPlasterboard and paint from 1.5 m, trims, doors and gaps, windows and glass, floor coverings, power, smoke alarms20
- S8Bathrooms, WC and laundry5-minute shower test, falls and wastes, screens, tiles flat and not drummy, silicone, taps, toilet, fans19
- S9KitchenCabinets and drawers, benchtop and splashback, sink and pipes, oven, cooktop, rangehood ducted outside, appliances10
- S10ServicesSwitchboard labels, safety switches tested, hot water, water hammer, heating and cooling, solar, data, alarm, tank12
- S11Shown how it worksMain switch, water shut-off, gas isolation, hot water relief valve, basic upkeep6
- S12Defects list and decisionEvery issue listed and photographed, fix-by dates agreed, both sign, defects period confirmed, insurance in your name10
- S13What your builder should be doingSite cleared, street and services undamaged, sediment controls, trade certificates collected, the builder's own inspection, defects register10
C16 - Practical Completion Inspection Checklist
$119.00 AUD
Last updated 28 Oct 2026 · Revision 5 · Free updates for life
Checklist Type: Major (Practical Completion Stage)
Form Factor: Fillable, print-ready PDF (A4, 45 pages)
When to use: Practical completion: inspecting your finished home before you accept it
A 164-point practical completion checklist for new Class 1a homes. Inspect every room and the outside, sight the certificates, and list every defect in writing before you accept.
✓ Authorship verified on the blockchain · View certificate
What it is
C16 is a fillable, 45-page checklist with 293 checks across 19 sections. It takes you through your finished home room by room, from the roof and gutters to every tap, switch, door and robe. It also covers the paperwork, keys and warranties you should collect before you accept the home.
Every check is a plain question with Fine, Later and Issue boxes. Key checks are marked, so you know which items you shouldn't accept the home without. A built-in defects register at the back lets you list every issue, have the builder sign it, and track each one until it's fixed.
C16 sits between C15 (Painting) and C17 (Handover) in our series, and it's one of our six Major stage checklists.
What it does
A practical completion inspection (PCI) is usually a walk-through with the supervisor, and it goes fast. Without a list, it's easy to look at the kitchen benchtop and forget the downpipes, or check the doors and never test the power points.
C16 gives you:
- A complete route through the home, so nothing gets skipped, from Before You Start through to Defects and Handover.
- A written record the builder signs, so every defect is agreed in writing before you pay.
- A collection list for everything you're owed: certificates, keys, remotes, devices, warranties and service information.
When to use it
- When the builder tells you the home has reached practical completion. Ask for it in writing, with the date.
- At the PCI itself. Book it in daylight, with power, water and gas connected, and bring a torch, tape measure, spirit level, power point tester and your CINS numbers (our numbered tags for marking each defect so it matches your photos and list; see the CINS post).
- Before you pay the final claim. Every Issue should be on the signed defects register, with a date for repair.
Why use it
Because once you've accepted the home, the conversation changes. Before practical completion, fixing a defect is part of finishing the job. After it, you're relying on your defects period and on proving the problem was there all along.
Some of the costliest items are easy to miss on the day:
- Water: ground that doesn't fall away from the slab, downpipes not connected to stormwater, and wet areas without the right falls.
- Certificates: the documents your home needs, such as electrical, plumbing, waterproofing, termite and smoke alarm certificates. C16 has 34 certificate checks.
- Keys and devices: every key, remote, valve key and device, and the warranty and service information for what's been installed.
What's in it for you
- Confidence on the day. You'll know what to look at and what to ask, and you'll have a reason to slow the walk-through down.
- A defects list that holds up. Dated, photographed with CINS numbers, and signed by the builder.
- Everything handed over. Nothing left in a site office or a supervisor's ute.
- A start on your defects period. Under Queensland's standard contracts, the builder must fix defects that appear within 12 months of practical completion (QBCC New Home Construction Contract, GC 29.1). Separately, under the QBCC Home Warranty Scheme, non-structural defects must appear within 6 months and be lodged within 7 months, so don't sit on anything you find. Your PCI record is the baseline for all of that.
What's inside: the 19 sections
| Section | Checks |
|---|---|
| S1Before you start | 8 |
| S2Certificates | 34 |
| S3Roof and gutters | 14 |
| S4Walls and cladding | 10 |
| S5Grounds and drains | 16 |
| S6Steps and decks | 9 |
| S7Tank, hot water and termite protection | 16 |
| S8Garage | 9 |
| S9Entry, doors and windows | 16 |
| S10Every room: finishes | 17 |
| S11Bedrooms and robes | 9 |
| S12Kitchen and appliances | 20 |
| S13Bathrooms, ensuite and WC | 24 |
| S14Laundry | 8 |
| S15Electrical, lighting and safety | 17 |
| S16Heating, cooling and ventilation | 7 |
| S17Keys, remotes and devices | 19 |
| S18Warranty and service information | 26 |
| S19Defects list and handover | 14 |
| Total | 293 |
Plus the defects register, a result page to total your marks, and notes pages.
Preview C16 · Get C16 for $119
Building from scratch? C16 is also in the Peace of Mind Starter bundle (with C4 and C17) and the Fixing to Handover bundle.
Keeping a record as you go? The Constructor Site Diary has a defects register you can carry straight into your PCI, and it comes free in every bundle.
A few honest caveats
- C16 is a guide, not professional advice. An independent building inspector will see things a homeowner won't, and many people use both.
- Your contract sets how practical completion and defects work. Read it before the PCI.
- Don't pay the final claim until every defect is either fixed or listed in writing with a date for repair.