Handover day feels like the finish line. You pay the final claim, get the keys and walk into your new home. But it's also the day you take on the risk: from here, the locks, the insurance and the job of reporting defects are yours. This post walks through our new C17 Handover Stage Checklist: what it is, what it does, when to use it, and why it's worth your time.

C17 at a glance

Handover: what to check and collect before you take the keys

111checks
11sections
3result options
22pages

Before the day: check the PC date, the final invoice and the documents.

On the day: walk through, then keys, spares, warranties and services. Tick Fine, Later (not yet) or Issue.

Before you leave: diarise the defects dates. S11 lists what your builder should have done: ask to see the records. Use the log on the last pages all year.

The 11 sections

  1. S1Before handover dayWritten notice, signed PCI defects document, date and place confirmed, daylight with services on, insurance and accounts in your name9
  2. S2Final claim and paymentInvoice matches the contract and signed variations, claim conditions met, bank details confirmed by phone, paid receipt9
  3. S3Certificates and documentsFinal inspection, home warranty, approvals and plans, engineer, waterproofing, electrical, plumbing, termite, energy, pool16
  4. S4Final walk-throughPCI items fixed, no new damage, clean, everything in the contract there and working, photos of every room8
  5. S5Keys, locks and accessLocks changed from construction keying, every key tried, meter and letterbox keys, garage remotes and codes reset13
  6. S6Remotes, tools and sparesRemotes, valve keys, plugs, oven trays and filters, touch-up paint, spare tiles and grout, one signed list8
  7. S7Warranties and manualsAppliances, hot water and solar, air-conditioning, windows and doors, waterproofing, roof and cladding, registrations10
  8. S8Services and safetyMeter readings, shut-offs and main switch, safety switches and smoke alarms tested, hot water and solar, after-hours number12
  9. S9Your defects periodLength and notice rules, defects in writing with photos, 6-month visit and 11-month walk-through diarised, regulator9
  10. S10Looking after your homeSlab edge and termite inspections, ground falls and soil moisture, pipes in walls, first-year plan, one home logbook8
  11. S11What your builder should be doingStreet and services undamaged, site cleared, the supervisor's own inspection, PCI defects signed off, safety switches and services commissioned9
Short on time? The “Check these 10” card on page 2 has the checks that matter most, and the “Documents to collect” box lists what to ask for. Use it at the handover meeting, after the practical completion inspection and before you take the keys. Educational guide only.

C17 - Handover Stage Checklist

$119.00 AUD

Last updated 28 Oct 2026 · Revision 5 · Free updates for life

Checklist Type: Major (Handover Stage)

Form Factor: Fillable, print-ready PDF (A4, 30 pages)

When to use: Handover: final payment, keys and taking possession of your home

A 111-point handover checklist for the day you take the keys. Cover the final claim, certificates, keys and codes, warranties and how to report defects on time.

Preview C17

✓ Authorship verified on the blockchain · View certificate

See all our checklists

Buy C17 – $119

What it is

C17 is a fillable, 15-page checklist with 109 checks across 10 sections. It covers the handover meeting from start to finish: paying the final claim safely, taking possession with your own locks and keys, collecting every warranty, and setting up your defects period so nothing slips.

Every check has Fine, Later and Issue boxes. Key checks are marked, a defects register lets you record anything new on the day, and a sign-off page records the dates that matter.

C17 follows C16 (Practical Completion) and leads into C18 (6 Month Maintenance). It's one of our six Major checklists, which cover the biggest stages of your build.


What it does

Handover is usually a short meeting with a lot riding on it. C17 turns it into a clear sequence:

  • Before the meeting: confirm the time and who's attending, bring your PCI checklist and defects register, arrange insurance and utilities in your name, and get every owner on the contract there or authorised.
  • On the day: pay exactly what's invoiced, in the way the contract allows, then collect certificates, keys, remotes, devices, spares and warranties, and test them before you sign.
  • After the meeting: know when your defects period ends, how defects must be notified, and what to look out for in the first months.

When to use it

  • A week or two before handover, for Sections 1 to 3: the meeting, the final payment and the documents.
  • At the handover meeting, for the rest: walk the home with the builder and test every key and remote.
  • Straight after, to set your defects period reminders and start your home care routine.

Why use it

Because a few things go wrong at handover more often than they should:

  • Paying before you're ready. The final claim is your strongest leverage. C17 helps you check that every PCI defect is either fixed or listed in writing with a date, before the money moves.
  • Trade keys still working. C17 checks that the locks are re-keyed to your key, so the builder's and trades' keys stop working.
  • Missing paperwork. Certificates, manuals and warranties are much harder to chase once the site team has moved on.
  • Losing track of the defects period. Under Queensland's standard contracts (QBCC New Home Construction Contract GC 29.1, Master Builders Level 2 cl 19), the builder must fix defects that appear within 12 months of practical completion. That runs from the date of practical completion on your builder's notice, not the handover date. C17 has you write the dates down and set reminders.

What's in it for you

  • A safe final payment, made once you know what you're getting.
  • Real possession of your home: your keys, your locks, your insurance and your utilities from day one.
  • Every warranty in one place, ready for when something stops working.
  • A defects period you control, with dates, reminders and a register, so you can report issues in writing as soon as you find them.

What's inside: the 10 sections

SectionChecks
S1Before the handover meeting10
S2Final payment11
S3Certificates and documents11
S4Keys, locks and security13
S5Devices, tools and spares9
S6Warranty and service information14
S7Utilities, services and safety10
S8Defects period and notification14
S9Looking after your home9
S10Final walk-through and sign-off8
Total109

Plus the defects register and a result page to total your marks and record the key dates.

Preview C17 · Get C17 for $119

C17 is also in the Peace of Mind Starter bundle (with C4 and C16) and the Fixing to Handover bundle.

Need a record of the build for the handover and the defects period? The Constructor Site Diary keeps your conversations, variations and defects registers in one place, with the key dates to diarise.


A few honest caveats

  • C17 is a guide, not legal or financial advice. Your contract sets the final payment, the defects period and how defects are notified, so read it before the meeting.
  • Report defects in writing as soon as you find them. Don't save them all for the end of the defects period.
  • Home warranty insurance has its own deadlines. In Queensland, non-structural defects must appear within 6 months of completion, and you must lodge with the QBCC within 7 months. Structural defects are covered for 6 years and 6 months.