Post 45: Blinding Down, Set-Out Done and Planning the Tanks
The blinding slab is down and set out, the sewer and stormwater tank walls have arrived, and the waterproofing for the tanks and basement walls is being designed ahead of a 250 m³ monolithic pour.
C22: The Colour Selections Checklist (every choice, made once and in writing)
Our C22 Colour Selections Checklist gives you 189 checks across 25 sections for your selection appointment, so every colour, finish and fitting is decided once, priced and written into your contract.
Post 44: Hand-Shaping Thickenings and Starting the Drainage
A week of careful work you can't see much of: hand-shaping the slab thickenings, setting height pins for the blinding, the first sheathed sewer pipe, and a dewatering failure that flooded the pits.
Post 43: Bulk Dig Done, Acoustic Screen Up and Setting Out the Slab
The bulk excavation is finished and the site finally looks like a building site. A DIY acoustic screen cuts the pump noise by about 25 dB, the grid goes up on the profiles, and the thickenings are being set out.
One checklist for every stage
Take them on site, tick off each check before you pay, and keep a record if something goes wrong later.
Start here
C1 Before Buying Land
Free
- Check the block before you buy or sign
- Email only, no card
Bundle
Land to Slab
$269save $86
- Every check from buying land to the slab
- The stage where hidden problems get buried
Best value
The Complete Set
$629AUD
- All 25 checklists, land to maintenance
- Includes The Trade Tool and CINS