The floor waste, also called a floor gully, is the grated drain in your bathroom or shower floor. It's not the most exciting part of your new home, but when it's in the wrong spot, or the floor doesn't fall to it, water ends up pooling on tiles or finding its way under doors.

Here's what you need to know so you can check it's done right during your build.

C13A - Waterproofing Design Checklist

$59.00 AUD

Last updated 28 Oct 2026 · Revision 3 · Free updates for life

Checklist Type: Minor

Form Factor: Fillable, print-ready PDF (A4, 23 pages)

When to use: Design stage: before waterproofing starts, while products and details can still change

A 59-point waterproofing design checklist. Settle shower types, set-downs, falls and one compatible set of products on paper, before anyone picks up a brush.

Preview C13A

See all our checklists

Buy C13A – $59

When is a floor waste required?

For a house (a Class 1 building), the NCC 2022 Housing Provisions Part 10.2 deals with wet area waterproofing and drainage. The shower area needs a waste so the water has somewhere to go. Outside the shower, the NCC doesn't require a floor waste in most bathrooms, laundries or toilets in a house.

Floor wastes are often installed anyway, particularly in upstairs bathrooms and laundries, because they give leaking hoses or an overflowing basin somewhere to drain before the water reaches the rooms below.

Apartments and other multi-unit buildings have stricter rules, but they're outside the scope of this post.

If you have a floor waste, the floor must fall to it

This is the part that matters most. Where the floor is graded to a floor waste, the NCC Housing Provisions (clause 10.2.12) set the fall to the waste at:

  • Minimum 1:80, so the water actually drains
  • Maximum 1:50, so the floor isn't steep enough to be a trip or slip hazard

The waste must sit at the lowest point. A waste that's higher than the surrounding tiles is a defect, not a design feature.

Queensland's extra rules: QDC MP4.5

Queensland adds requirements in the Queensland Development Code MP4.5. In general, if a wet area has a floor waste, the floor needs to be graded to it. There are exceptions where the floor doesn't need to be graded to a non-mandatory floor waste:

  • All vessels (basins, tubs, baths) have built-in overflow protection, and flood-stop safety valves are fitted to all flexible hoses in the room; or
  • Each entrance to the wet area has a linear drain across the full width of the entrance; or
  • Each entrance has a weir at least 10 mm above the height of the floor waste, with any ramp within the door jamb area no steeper than 1:8.

Also:

  • If there's no floor waste, the floor doesn't need to be graded.
  • An area of floor separated from the entrance by a graded area doesn't have to be graded itself (see figure A5(5) in QDC MP4.5).

Waterproofing around the waste

The whole shower floor, and the floor and wall areas required by AS 3740 and the NCC, must be waterproofed, not just a small patch around the waste. At the waste, the membrane is turned down into a puddle flange so any water that gets through the tiles and grout drains into the waste instead of sitting under the floor.

My C13A Waterproofing Design and C13B Waterproofing Installation checklists walk you through what to check before the tiler covers it up.

Size and type

Your plumber sizes and installs the waste to AS/NZS 3500.2. Your job isn't to pick a flow rate. It's to check the waste is in the lowest point and the floor falls to it. Grates come in plastic, stainless steel and tile-insert styles, so choose one that suits the look of the room. Tile-insert and linear grates should still be removable for cleaning.

Common problems I see on site

  • No fall, or a fall the wrong way. Water ponds in a corner or runs out the door.
  • Waste set too high. Usually from poor screed or tile thickness planning.
  • Missing puddle flange or a membrane that stops short. Water gets under the tiles and stays there.
  • Debris in the pipe. Grout, tile offcuts and screed get washed down the waste during construction.

On that last point, ask that wastes are fitted with a proper removable cap during construction. Don't stuff a rag, bag or sponge in the pipe; they get forgotten and cause blockages.

What to check at practical completion

  1. Run water in the shower and on the bathroom floor. It should drain to the waste with no ponding.
  2. Check the construction caps have been removed and the grate is fitted.
  3. Make sure the waste runs freely and doesn't smell. A dry trap can let sewer gas in, so pour water into rarely used wastes regularly.
  4. Look for any gap or cracking around the grate.

If a floor doesn't drain properly, report it to your builder in writing. Under a Queensland standard contract you have 12 months from practical completion to notify defects.